Marina Dredging Starts Today

Fond du Lac’s Public Works Department informs us there will be dredging at the marina entrance starting Monday. The City’s contractor, PCi Dredging, will be dredging a channel at the Marina entrance located east of the lighthouse. The dredge area will be approximately 80’ x 250’ and work will begin on the western side of the entrance. Markers and buoys will be placed indicating a passage channel to the east during this operation. Once the west side is completed the dredge will be moved to work on the east side with markers and buoys again being placed indicating a passage channel to the west during this operation. The dredge line which will cross the channel at this point will be at a minimum depth of 4’. The dredge operator will be monitoring VHF Channel 10 during the work. Please use caution when entering and exiting the Harbor during this operation. It is anticipated that work will be complete by Friday, August 15th with no work on the weekend of August 9-10th.